Progress This Week
- Demolition of 40 rooms, including halls, in the wing A, both upstairs and downstairs.
- Demolition of all flooring tiles in the designated areas.
- Demolition of tubs, vanities, and toilets in 40 rooms.
- Completion of plumbing in 30 rooms, ensuring water connections are established.
- Completion of electrical work in 35 rooms, including all layout installations, ceiling lights, receptacles, and cabinet layouts.
- The exterior paint of the property has been completed.
- The event center has been painted and is finished.
- First-floor ceiling insulation has been installed along with plumbing and electrical work.
Two-week Ahead Plan