Brownsville Project Report – 02/02


  • Bathroom work: All tubs and Durok installation are to be completed tomorrow for a total of 40 rooms
  • Exterior paint: Tomorrow for the entire exterior, and exterior trims on Friday
  • Flooring: Completion of ceramic flooring on the 1st floor for all 40 rooms
  • Sheetrock: Demolition completed for 40 rooms
  • Cabinets: 20 sets are rea1dy, including closets
  • Electrical layouts: Completed for 25 rooms, awaiting feeders
  • Plumbing: Drain setup completed for 40 rooms, and water lines set up for kitchenettes

 


  • Completion of a minimum of 20 rooms
  • Hallways painting
  • Sheetrock installation in the rooms
  • Cabinets fitting Doors installation
  • Trim work

 