PROGRESS THIS WEEK
- Bathroom Work: Advanced progress on all tubs and Durok installation; set to be completed tomorrow for a total of 40 rooms
- Flooring: Completed ceramic flooring on the 1st floor for all 40 rooms
- Sheetrock: Completed demolition for 40 rooms
- Cabinets: 20 sets are ready, including closets
- Electrical Layouts: Ready for 25 rooms, awaiting feeders
- Plumbing: Completed drain setup for 40 rooms
- Water Lines: Completed installation for kitchenettes in 40 rooms
TWO-WEEK AHEAD PLAN
- Exterior Paint: Scheduled for tomorrow for the entire exterior, with exterior trims planned for Friday
- Sheetrock: installation for 40 rooms
- Tape and float application
- Cabinet installation
- Finishing trims for both electrical and plumbing