Brownsville Project Report – 03/01

Progress This Week

  • Successful installation of hot and cold water lines in the laundry room using precision pressure drilling techniques
  • Identification and confirmation of the main drain 
  • Anticipated completion of storage units within the current week
  • Progress contingent upon the approval and release of inspection by city authorities

Two-Week Plan Ahead

  • Ongoing excavation activities
  • Schedule installation of doors next week
  • Commencement of painting and finishing trims 

PAST DRAW