PROGRESS THIS WEEK
- Painting cabinets for all 80 units completed
- Rooms sanded, scraped, and prepared for tiling and flooring
- Plumber has installed new shower valves in all 40 rooms
TWO-WEEK PLAN AHEAD
- Sheetrocking, taping, and floating rooms
- Painting of rooms
- Trimming and cabinet installation
- Installation of pre-built and painted closets and shelves