Progress This Week
- Final fire suppression inspection
- Final fire alarm installation.
- Final door replacement.
- Debris removal.
- Gas meter increase and gas pressure test.
Two-week Ahead Plan
- Finalize rooms with furnishings, including blankets, towels, and other housewares.
- Finalize utility services.
- Finalize landscaping.
- Continue leasing the rooms.
- Secure certificate of occupancy for all the units.