Progress This Week
Gas meters must be upgraded as per gas company; new gas meters are being designed and to be installed within a few weeks
All other construction is complete, and units are being prepped for leasing
We are waiting for a certificate of occupancy from the Fire Marshall
Tenants are touring the property and submitting applications
Shopping Lenders for a refinance
Two-Week Ahead Plan
Begin to fill units
Secure refinance terms
Targeting first investor distribution date in early Q2