PROGRESS THIS WEEK
- Bathroom work: All tubs and Durok installation are to be completed tomorrow for a total of 40 rooms
- Exterior paint: Tomorrow for the entire exterior, and exterior trims on Friday
- Flooring: Completion of ceramic flooring on the 1st floor for all 40 rooms
- Sheetrock: Demolition completed for 40 rooms
- Cabinets: 20 sets are rea1dy, including closets
- Electrical layouts: Completed for 25 rooms, awaiting feeders
- Plumbing: Drain setup completed for 40 rooms, and water lines set up for kitchenettes
TWO-WEEK AHEAD PLAN
- Completion of a minimum of 20 rooms
- Hallways painting
- Sheetrock installation in the rooms
- Cabinets fitting Doors installation
- Trim work
UPDATE PHOTOS