Brownsville Project Report – 02/09


  • Bathroom Work: Advanced progress on all tubs and Durok installation; set to be completed tomorrow for a total of 40 rooms
  • Flooring: Completed ceramic flooring on the 1st floor for all 40 rooms
  • Sheetrock: Completed demolition for 40 rooms
  • Cabinets: 20 sets are ready, including closets
  • Electrical Layouts: Ready for 25 rooms, awaiting feeders
  • Plumbing: Completed drain setup for 40 rooms
  • Water Lines: Completed installation for kitchenettes in 40 rooms

 


  • Exterior Paint: Scheduled for tomorrow for the entire exterior, with exterior trims planned for Friday
  • Sheetrock: installation for 40 rooms
  • Tape and float application
  • Cabinet installation
  • Finishing trims for both electrical and plumbing

 