Brownsville Project Report – 02/16

Progress This Week

  • Water lines and drains for Rooms 101-120 have been installed
  • Water lines and kitchen drains for Rooms 201-220 have been installed
  • Plans and preparation to build a 40-unit storage center
  • Additional paint touch-ups
  • Delivered cabinets to the job site for 20 units; commencing work on the other 20 for Wing A
  • Completing plumbing work, specifically finishing shut-off valves in hallways

Two-week Ahead Plan

  • Continue storage center build-out
  • Install sheetrock, tape, and float
  • Prepare flooring for installation
  • Begin patching rooms and hallways
  • Start laundry set up on Monday, February 19th
  • Break concrete and set drain lines for rough and plumbing for the laundry room
  • Apply the last coat of paint in the event center lobby and hallways