Progress This Week
- Ensure doors are properly sealed and trimmed on all 40 storage units for a finished look
- Focus on plumbing tasks, especially for the laundry area
- Break concrete to prepare for washer installation
- Established preliminary drain connections, emphasizing rough plumbing
- Integrated 4″ PVC pipes into existing drains for secure connections
- Set up culverts to improve laundry drainage
- Started installing the wall shower ceramics
- Scheduled a plumber to connect shut-off valves on all 40 units by the end of the week
Two-Week Plan Ahead
- Continue making cabinets and closets
- Paint the 1×4 trim once it’s ready, the trim will undergo a painting process for a finished appearance