Progress This Week
- Successful installation of hot and cold water lines in the laundry room using precision pressure drilling techniques
- Identification and confirmation of the main drain
- Anticipated completion of storage units within the current week
- Progress contingent upon the approval and release of inspection by city authorities
Two-Week Plan Ahead
- Ongoing excavation activities
- Schedule installation of doors next week
- Commencement of painting and finishing trims