PROGRESS THIS WEEK
- Completed 20-bathroom shower ceramics
- All storage units have been completed
TWO-WEEK PLAN AHEAD
- Continue sheetrock installation
- Proceed with painting tasks
- Complete insulation installation







PROGRESS THIS WEEK
TWO-WEEK PLAN AHEAD