PROGRESS THIS WEEK
- Prepared wood: filled holes, sanded, primed, and painted wood surfaces
- Installed 1×4 trim for all rooms, closets (40 total), and kitchenettes in 40 rooms
- Applied primer and painted storage units, installed doorknobs
- Prepared rooms by clearing remaining thin-set debris for new flooring installation
TWO-WEEK PLAN AHEAD
- Work on plumbing, focusing on shutting off valves