Brownsville Project Report – 05/03


  • Floors prepped for tile installation completed
  • Installed 60 sets of kitchen cabinets and closets
  • Currently building the remaining 20 sets of kitchenettes
  • Lobby area’s composition shingles replaced
  • Demolition and installation tasks completed

  • Completion of remaining building tasks
  • Anticipated release of pool permit
  • Continuing discussions with city inspector for indoor room work