Brownsville Project Report – 06/07


  • Proceeding with tile install for units 1-40
  • Beginning cabinet and closet production for units 41-80
  • Have received city approval for: Electrical, Gas, Mechanical, Planning and Zoning, and Fire Department
  • Remaining items to be approved by city: Plumbing, Public Utilities Cross Connection and Backflow
  • Andrew Onsite for the second time in a month to push the project along