STATUS UPDATE
- • Final approval for gas turn on for the West side still pending
TWO-WEEK AHEAD PLAN
- Goal to have the property 90% leased within 90 days
- Gas test and turn on for units 1 through 21 scheduled Monday morning
STATUS UPDATE
TWO-WEEK AHEAD PLAN